Friday 11 August 2017

Cabinet Summary - new cabinets LIVE! and new rollout dates

Cabinet 1 - in the village - has been live since Dec 2015

Cabinet 2 - Letterwalton/Pony Park/Tyree/North Benderloch IS NOW LIVE and ACCEPTING ORDERS!

Cabinet 3 - South Shian opp. Shenavallie junction - is apparently now LIVE, but not yet accepting orders. ETA Aug 2017

Cabinet 4 - (opposite Ardbhatan), towards South Shian is not yet connected for fibre and power, but new BT poles and overhead lines have been installed this week. ETA Jan 2017

Cabinet 5 - (Barcaldine, near junction with Glen Salcah) - not yet connected for fibre and power. ETA November 2017

BT availability checker shows cabinet 4 as still being connected. Cabinet 3 (Shenavallie) is activated but not yet accepting orders; presumably awaiting cabinet 4 to be wired up.



Fibre CabinetFibre StatusPhaseProperties
Passed
VendorApprox
Post Code
Cabinet P1  FTTC Available from 18th December 2015  Phase BDUK HIE 12a   149  Huawei  PA37 1PY  
Cabinet P2  FTTC being Activated, live due by August 2017  Phase BDUK HIE 16a     Huawei  PA37 1RY  
Cabinet P3  FTTC being Activated, live due by August 2017  Phase BDUK HIE 16a     Huawei  PA37 1QU  
Cabinet P4  FTTC being Connected, live due by January 2017  Phase BDUK HIE 16a     Huawei  PA37 1QR  
Cabinet P5  FTTC being Connected, live due by November 2017  Phase BDUK HIE 16a     Huawei  PA37 1SL  