Tuesday 11 October 2016

ETA January 2017..?

ETA for two of the Benderloch cabinets now back to January 2017 rather than June 2017.
Cabinets P3 and P4 (Shenavallie and Ardbhatan if the stickers on the new green cabinets are anything to go by) now due go-live by January 2017 rather than June 2017 which is nice.


Fibre CabinetFTTC StatusPhaseFTTP StatusProperties
Passed
VendorApprox
Post Code
Cabinet P1  FTTC Available from 18th December 2015  Phase BDUK HIE 12a      149  Huawei  PA37 1PY  
Cabinet E_2  FTTC doing Design, live due by January 2017  Phase BDUK HIE 16a        Huawei    
Cabinet P2  FTTC doing Field Survey, live due by June 2017  Phase BDUK HIE 16a        Huawei  PA37 1RY  
Cabinet E_3  FTTC doing Design, live due by January 2017  Phase BDUK HIE 16a        Huawei    
Cabinet P3  FTTC being Connected, live due by January 2017  Phase BDUK HIE 16a        Huawei  PA37 1QU  
Cabinet E_4  FTTC doing Design, live due by January 2017  Phase BDUK HIE 16a        Huawei    
Cabinet P4  FTTC being Connected, live due by January 2017  Phase BDUK HIE 16a        Huawei  PA37 1QR  
Cabinet P5  FTTC doing Field Survey, live due by June 2017  Phase BDUK HIE 16a        Huawei  PA37 1SG  
Cabinet E_6  FTTC doing Design, live due by January 2017  Phase BDUK HIE 16a        Huawei    