Order now complete on a Fibre broadband package Here's my connection speed:
real-world data transfer (speedtest.net anyway) gives pretty close to this:
Our line length is under 30 metres.
A neighbour with 1.3KM line length is getting 30Mb/s
Documenting my findings about superfast broadband rollout in Benderloch, Argyll
| Fibre Cabinet | Fibre Status | Phase | Properties Passed | Vendor | Approx Post Code |
| Cabinet P1 | FTTC Available from 18th December 2015 | Phase BDUK HIE 12a | 149 | Huawei | PA37 1PY |
| Cabinet P2 | FTTC being Activated, live due by August 2017 | Phase BDUK HIE 16a | Huawei | PA37 1RY | |
| Cabinet P3 | FTTC being Activated, live due by August 2017 | Phase BDUK HIE 16a | Huawei | PA37 1QU | |
| Cabinet P4 | FTTC being Connected, live due by January 2017 | Phase BDUK HIE 16a | Huawei | PA37 1QR | |
| Cabinet P5 | FTTC being Connected, live due by November 2017 | Phase BDUK HIE 16a | Huawei | PA37 1SL |

Exchange name: Ledaig| Cabinet P2 | FTTC being Connected, live due by March 2017 | Phase BDUK HIE 16a | Huawei | PA37 1RY | |
| Cabinet P3 | FTTC being Connected, live due by January 2017 | Phase BDUK HIE 16a | Huawei | PA37 1QU | |
| Cabinet P4 | FTTC being Connected, live due by January 2017 | Phase BDUK HIE 16a | Huawei | PA37 1QR | |
| Cabinet P5 | FTTC doing Field Survey, live due by June 2017 | Phase BDUK HIE 16a | Huawei | PA37 1SG |
| Cabinet P1 | FTTC Available from 18th December 2015 | Phase BDUK HIE 12a | 149 | Huawei | PA37 1PY |
| Cabinet E_2 | Fibre Not Available | Phase BDUK HIE 16a | Huawei | ||
| Cabinet P2 | FTTC doing Field Survey, live due by June 2017 | Phase BDUK HIE 16a | Huawei | PA37 1RY | |
| Cabinet E_3 | Fibre Not Available | Phase BDUK HIE 16a | Huawei | ||
| Cabinet P3 | FTTC being Connected, live due by January 2017 | Phase BDUK HIE 16a | Huawei | PA37 1QU | |
| Cabinet E_4 | Fibre Not Available | Phase BDUK HIE 16a | Huawei | ||
| Cabinet P4 | FTTC being Connected, live due by January 2017 | Phase BDUK HIE 16a | Huawei | PA37 1QR | |
| Cabinet P5 | FTTC doing Field Survey, live due by June 2017 | Phase BDUK HIE 16a | Huawei | PA37 1SG | |
| Cabinet E_6 | Fibre Not Available | Phase BDUK HIE 16a | Huawei |
| Fibre Cabinet | FTTC Status | Phase | FTTP Status | Properties Passed | Vendor | Approx Post Code |
| Cabinet P1 | FTTC Available from 18th December 2015 | Phase BDUK HIE 12a | 149 | Huawei | PA37 1PY | |
| Cabinet E_2 | FTTC doing Design, live due by January 2017 | Phase BDUK HIE 16a | Huawei | |||
| Cabinet P2 | FTTC doing Field Survey, live due by June 2017 | Phase BDUK HIE 16a | Huawei | PA37 1RY | ||
| Cabinet E_3 | FTTC doing Design, live due by January 2017 | Phase BDUK HIE 16a | Huawei | |||
| Cabinet P3 | FTTC being Connected, live due by January 2017 | Phase BDUK HIE 16a | Huawei | PA37 1QU | ||
| Cabinet E_4 | FTTC doing Design, live due by January 2017 | Phase BDUK HIE 16a | Huawei | |||
| Cabinet P4 | FTTC being Connected, live due by January 2017 | Phase BDUK HIE 16a | Huawei | PA37 1QR | ||
| Cabinet P5 | FTTC doing Field Survey, live due by June 2017 | Phase BDUK HIE 16a | Huawei | PA37 1SG | ||
| Cabinet E_6 | FTTC doing Design, live due by January 2017 | Phase BDUK HIE 16a | Huawei |
| Cabinet P1 | FTTC Available from 18th December 2015 | Phase BDUK HIE 12a | 149 | Huawei | PA37 1PY | |
| Cabinet E_2 | FTTC doing Design, live due by January 2017 | Phase BDUK HIE 16a | Huawei | |||
| Cabinet P2 | FTTC doing Design, live due by July 2017 | Phase BDUK HIE 16a | Huawei | |||
| Cabinet E_3 | FTTC doing Design, live due by January 2017 | Phase BDUK HIE 16a | Huawei | |||
| Cabinet P3 | FTTC doing Design, live due by July 2017 | Phase BDUK HIE 16a | Huawei | |||
| Cabinet E_4 | FTTC doing Design, live due by January 2017 | Phase BDUK HIE 16a | Huawei | |||
| Cabinet P4 | FTTC doing Design, live due by July 2017 | Phase BDUK HIE 16a | Huawei | |||
| Cabinet P5 | FTTC doing Design, live due by July 2017 | Phase BDUK HIE 16a | Huawei | |||
| Cabinet E_6 | FTTC doing Design, live due by January 2017 | Phase BDUK HIE 16a | Huawei |